At the end of a capital project, thousands of tags, data sheets and documents move from the contractor to the owner. Too often they arrive late, incomplete and in a different format for every contractor. CFIHOS exists to fix exactly that.
CFIHOS in one sentence
CFIHOS — the Capital Facilities Information Handover Specification — is an industry standard that defines what information a contractor should hand over to an owner-operator, and in what structure. It gives everyone the same list of equipment classes, the properties each class needs, and the document types that go with them. The specification is developed by the industry and today maintained under IOGP, the International Association of Oil & Gas Producers.
Why it matters
- Less rework. Contractors know the requirement from day one instead of discovering it at handover.
- Same structure from every contractor. Data from different packages can be combined without manual mapping.
- Faster start-up. Maintenance, inspection and operations systems can be loaded early, not months after first oil or first batch.
- A register you can trust. Maintenance teams find the right data sheet and spare part without searching.
How to implement it — step by step
- Agree scope
- Map classes
- Contract requirement
- Validate early
- Load into O&M
- Agree the scope. Decide which classes, properties and documents you really need for operations and maintenance — not everything the standard allows.
- Map to your systems. Connect CFIHOS classes to the structure of your CMMS/EAM and document system, so the data lands in the right place.
- Put it in the contract. Give contractors templates and validation rules at the start of the project.
- Validate continuously. Check deliveries as they come in, with clear quality scores — not in one big push at the end.
- Load and keep it current. Load into operations systems before start-up and set up governance so the data stays correct.
Common pitfalls
- Treating handover as a document dump at the end of the project.
- Asking for every possible property instead of what operations really uses.
- No owner for the data after handover — so quality slowly drops.